已收录 268921 条政策
 政策提纲
  • 暂无提纲
Behavior of Capstone and Honeywell microturbine generators during load changes
[摘要] This report describes test measurements of the behavior of two microturbine generators (MTGs) under transient conditions. The tests were conducted under three different operating conditions: grid-connect; stand-alone single MTG with load banks; and two MTGs running in parallel with load banks. Tests were conducted with both the Capstone 30-kW and Honeywell Parallon 75-kW MTGs. All tests were conducted at the Southern California Edison /University of California, Irvine (UCI) test facility. In the grid-connected mode, several test runs were conducted with different set-point changes both up and down and a start up and shutdown were recorded for each MTG. For the stand-alone mode, load changes were initiated by changing load-bank values (both watts and VARs). For the parallel mode, tests involved changes in the load-bank settings as well as changes in the power set point of the MTG running in grid-connect mode. Detailed graphs of the test results are presented. It should be noted that these tests were done using a specific hardware and software configuration. Use of different software and hardware could result in different performance characteristics for the same units.
[发布日期] 2001-07-01 [发布机构] Lawrence Berkeley National Laboratory
[效力级别]  [学科分类] 
[关键词] Power Range 10-100 Kw;Start-Up;Load Analysis;Performance Testing;42 Engineering [时效性] 
   浏览次数:66      统一登录查看全文      激活码登录查看全文