Supervisory Control and Data Acquisition System (SCADA) Substation C3-3 Acceptance Test Procedure
[摘要] The purpose of this acceptance test procedure (ATP) is to demonstrate that the newly installed Supervisory Control and Data Acquisition (SCADA) computer system functions as intended by the design.
[发布日期] 2000-10-17 [发布机构] Fluor Hanford, Inc.
[效力级别]  [学科分类] 
[关键词] 99 General And Miscellaneous//Mathematics, Computing, And Information Science;12 Management Of Radioactive Wastes, And Non-Radioactive Wastes From Nuclear Facilities;Computerized Control Systems;Performance Testing;Storage Facilities [时效性] 