[摘要] An overview of NASA Stennis Space Center's (SSC) A-3 Subscale Diffuser Test (SDT) Project is presented. The original scope of the SDT Project, conducted from April 2007 to January 2008, collected data to support mitigation of risk associated with design and procurement activities of the A-3 Test Stand Project, an effort to construct a simulated altitude test facility at SSC in support of NASA's Constellation Program. Follow-on tests were conducted from May 2008 through August 2009, utilizing the SDT test setup as a testbed for additional risk mitigation activities. Included are descriptions of the Subscale Diffuser (SD) test article, the test facility configuration, and test approaches.
[发布日期] 2009-08-03 [发布机构]