EC Transmission Line Risk Identification and Analysis
[摘要] The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.
[发布日期] 2012-04-01 [发布机构]
[效力级别] [学科分类] 电力
[关键词] DESIGN;FUNCTIONALS;IMPLEMENTATION;PLANNING;POWER TRANSMISSION LINES;PROCUREMENT;PRODUCTION;TESTING [时效性]